Reconstruction of K Street

  • Increase font size
  • Default font size
  • Decrease font size
Schedule
E-mail

PLANNING PHASE
June 2009 Initiated Environmental Assessment
September 15, 2009 Submitted Federal Funding Application
October 14, 2009 Public Hearing
December 2009 Final Environmental Assessment / Preferred
Alternative Identified
DESIGN PHASE
Fall 2009
Project Design Initiated
TBD Public Meeting
Early February 2010 Preliminary Design to be completed
February 17, 2010 Announcement of Federal Funding recipients
If DDOT receives Federal stimulus money to fund this project, then the project schedule will continue...
Mid 2010 Complete Design
Mid 2010 Begin Construction