| PLANNING PHASE |
|
|---|---|
| June 2009 | Initiated Environmental Assessment |
| September 15, 2009 | Submitted Federal Funding Application |
| October 14, 2009 | Public Hearing |
| December 2009 | Final Environmental Assessment / Preferred Alternative Identified |
| DESIGN PHASE |
|
| Fall 2009 |
Project Design Initiated |
| TBD | Public Meeting |
| Early February 2010 | Preliminary Design to be completed |
| February 17, 2010 | Announcement of Federal Funding recipients |
| If DDOT receives Federal stimulus money to fund this project, then the project schedule will continue... |
|
| Mid 2010 | Complete Design |
| Mid 2010 | Begin Construction |





